Current primary focus
North Nigeria power plant
The main focus for Aqua Energy is a dam already constructed in the North of Nigeria. There are hundred of businesses close-by that have been forced to stop work due to lack of diesel to generate electricity.
The State Governor have asked Aqua Energy to move swiftly because his state is in dire need of electricity.
| Rated net head: | HN = 41 m |
| Rated discharge: | QA = 14 m3/s |
| Turbine output: | PT = 5079 kW |
| Rated speed: | n1 = 375 rpm |
| Runaway speed: | nD = 694 rpm |
| Runner outlet diameter: | D2 = 1382 mm |
| Permissible suction head: | hS = +2,5 m |
Water cleaning plant
There will be a water cleaning system (reverse osmosis solution developed by Aqua Vitale in Norway) with bottling and filling plant.
- Production will be 1,5 million litres of clean water per day.
Development details
- Type of development:
- Canal and Penstock
- Planned production:
- 3 * 5079 kW = 15MW at full capacity
- Date of operating license:
- Being obtained (3 months processing time)
- Date of contract with landowner:
- Ready to be signed