Current primary focus

North Nigeria power plant

The main focus for Aqua Energy is a dam already constructed in the North of Nigeria. There are hundred of businesses close-by that have been forced to stop work due to lack of diesel to generate electricity.

The State Governor have asked Aqua Energy to move swiftly because his state is in dire need of electricity.

Technical data: 3 GHE FRANCIS SPIRAL TURBINE
Rated net head: HN = 41 m
Rated discharge: QA = 14 m3/s
Turbine output: PT = 5079 kW
Rated speed: n1 = 375 rpm
Runaway speed: nD = 694 rpm
Runner outlet diameter: D2 = 1382 mm
Permissible suction head: hS = +2,5 m

Water cleaning plant

There will be a water cleaning system (reverse osmosis solution developed by Aqua Vitale in Norway) with bottling and filling plant.

- Production will be 1,5 million litres of clean water per day. 

Back to projects

Development details

Type of development:
Canal and Penstock
Planned production:
3 * 5079 kW = 15MW at full capacity
Date of operating license:
Being obtained (3 months processing time)
Date of contract with landowner:
Ready to be signed

Nigeria meeting

 